March 20, 2009

Further Update From The Grove Spa Resort Construction Site

We have a mass of photographs coming through from the Grove Spa Resort site as our intrepid operations manager, Jonathan Fairhurst, known in the company as "Nanook of the North" has been on-site all week.

This is his latest report today:

As you'll see there is a huge amount of activity today on both plots. The membrane has been laid under the Spa building and Blocks E & F and GCC were in the process of pouring the concrete on top.

The temporary wooden boundaries to the rear of Blocks C & D were also being erected. The concrete base for the lifts had been delivered and were being manoeuvred into position. On Plot A, the initial concrete base had been completed and the steel reinforcement was being constructed - this was mostly done for Block B.






Have a great weekend

Dominic Farrell