March 12, 2011
March 11th 2011
February 16, 2011
Images of the Hydrotherapy Pool & Spa
February 1, 2011
The Grove Spa Resort 1st February 2011


October 20, 2010
Grove Spa Resort Blog Update 19th October 2010
We are delighted to have taken possession of Plot A of The Grove Spa Resort from GCC. It has been a challenging year for everyone involved, given the seismic changes in world economic conditions but we are proud to have delivered a top class scheme. It is looking really excellent now the outside work has been finished and the pools have been filled.
View of Blocks B and G from the poolside |
We have had a busy programme of handovers to clients and this continues throughout October and November. The feedback is very positive and clients have been enjoying the serenity and views from the resort when staying overnight.
During the day the site is a hive of activity with contractors finishing the last details, clients taking possession of properties, furniture deliveries and utility companies doing the final sign-off checks.
Plot A from the Spa building |
One of the giant Jacuzzis in action |
One of the pool technicians demonstrated today how the pool water, which is cleaned without chlorine using an environmentally-friendly process, is cleaner than the municipal tap water and can safely be drunk.
Pools on Plot A |
The decking and gardens on Plot B |
View of Plot A from Block H |
Work continues on Plot B (comprising Blocks C, D, E and F) to the end of the month when all private apartments will be ready, all external communal works completed and GCC hand over this plot. Work will continue on the Spa building, shop, restaurant, green area and roads to the end of the year.
Planting begins on Plot B |
Spa reception building |
Installation of the decking around the pool in front of C-Block |
One of the townhouses in D-Block is now fully furnished and provides a cool retreat from the heat and dust of the building site.
Townhouse |
Master Bedroom |
Second Bedroom |
September 15, 2010
First client takes possession of property at The Grove Spa Resort
David Pepper was the first client to take delivery of his apartment on 15th September 2010. David is pictured here in the kitchen of his penthouse in Block A receiving the keys from Joanne Patterson from InvestinCyprus.com Developers Customer Services. David inspected the apartment, transferred his utility accounts and installed all his furniture and window coverings in a jam-packed short trip to the island. He will return in October for a holiday with his family in his new property.
David Pepper receives the keys to his penthouse in Block A from Joanne Patterson |
September 8, 2010
Site Progress Meeting 8th September 2010
Plot A |
The apartments on Plot A, ie those in Blocks A, B, G and H are now finished and fully snagged internally. We are waiting for delivery of the last pieces of expansion joint materials to enable the rest of the communal external area to be completed.
The site was due for handover by the construction company on 1st September but due to a few items still to finish off externally, as well as waiting for the electricity authority to finish the testing and commissioning of the electricity supply to each apartment, we will now take possession of the site on 5th October. Delivery of Plot B (comprising Blocks C, D, E and F) will be on 20th October. This new handover timetable does not affect the delivery of the apartments which are finished and undergoing final snagging ahead of the delivery to clients between 15th September and 15th November.
Kitchen of Block D Townhouse |
In the communal external spaces, the Gripstone areas are almost completed and the wooden decking around the pools has begun to be installed.
Installing the wooden decking |
All garden areas have now been planted and the artificial grass installed between Blocks A, H, G and B which gives a cool, calm feeling to the resort.
View from ground floor apartment in B block |
View of resort from upper floor of Block H | View of Block B |
The utility companies have finished the installation of water and electricity connections around the development so the road construction is now underway. With so much messy work going on around the edges of the resort to complete the roads and pathways we are delaying filling the pools until the end of the month.
Laying out the visitor car park next to Block G | Finishing the main car park of the Spa building |
We spent time this week with potential operators of the restaurant and supermarket and also continued with the interviews for resort staff. The Spa building continues to shape up well.
Spa building reception |
Roof top café bar | View from the gym |
Sound proofed ceiling of the dance studio | Dominic and Joanne in the TV room |
View of plot B from Spa building |
Back of Block H |
The underground car parks are finished as are the ramps in and out. The fire shutters will be installed next and the individual car park space markings.
Underground car park entrance | Underground car park exit |
Underground car park |
The next site meeting will take place on Tuesday 5th October.