February 16, 2011

Images of the Hydrotherapy Pool & Spa

Hydrotherapy pool with massage jets

Hydrotherapy pool with Jacuzzi

Spa centre meet and greet area

Chromatherapy relaxation room

One of the seven treatment rooms

February 1, 2011

The Grove Spa Resort 1st February 2011

Night view of the Spa building from the resort

Pool view at night

Main entrance to the Spa building

Reception area

Gymnasium ready for fit-out

Dance / aerobic studio on the first floor of the Spa building

Roof top cafe bar

Roof top cafe bar with mountain views

Deck in front of Spa building

From Spa deck to C and D blocks

Views from G Block

View to B Block from G Block

October 20, 2010

Grove Spa Resort Blog Update 19th October 2010

We are delighted to have taken possession of Plot A of The Grove Spa Resort from GCC. It has been a challenging year for everyone involved, given the seismic changes in world economic conditions but we are proud to have delivered a top class scheme.  It is looking really excellent now the outside work has been finished and the pools have been filled.

View of Blocks B and G from the poolside

We have had a busy programme of handovers to clients and this continues throughout October and November. The feedback is very positive and clients have been enjoying the serenity and views from the resort when staying overnight.

During the day the site is a hive of activity with contractors finishing the last details, clients taking possession of properties, furniture deliveries and utility companies doing the final sign-off checks.

Plot A from the Spa building
Plot A from the Spa building
One of the giant Jacuzzis in action
One of the giant Jacuzzis in action

One of the pool technicians demonstrated today how the pool water, which is cleaned without chlorine using an environmentally-friendly process,  is cleaner than the municipal tap water and can safely be drunk.

Pools on Plot A
Pools on Plot A
The decking and gardens on Plot B
The decking and gardens on Plot B
View of Plot A from Block H
View of Plot A from Block H

Work continues on Plot B (comprising Blocks C, D, E and F) to the end of the month when all private apartments will be ready, all external communal works completed and GCC hand over this plot.  Work will continue on the Spa building, shop, restaurant, green area and roads to the end of the year.

Planting begins on Plot B
Planting begins on Plot B
Spa reception building
Spa reception building
Installation of the decking around the pool in front of C-Block
Installation of the decking around the pool in front of C-Block

One of the townhouses in D-Block is now fully furnished and provides a cool retreat from the heat and dust of the building site.   

Townhouse
Townhouse
Master Bedroom
Master Bedroom
Second Bedroom
Second Bedroom

 

September 15, 2010

First client takes possession of property at The Grove Spa Resort

David Pepper was the first client to take delivery of his apartment on 15th September 2010. David is pictured here in the kitchen of his penthouse in Block A receiving the keys from Joanne Patterson from InvestinCyprus.com Developers Customer Services. David inspected the apartment, transferred his utility accounts and installed all his furniture and window coverings in a jam-packed short trip to the island. He will return in October for a holiday with his family in his new property.

David Pepper receives the keys to his penthouse in Block A from Joanne Patterson

David Pepper receives the keys to his penthouse in Block A from Joanne Patterson

September 8, 2010

Site Progress Meeting 8th September 2010

Plot A
Plot A

The apartments on Plot A, ie those in Blocks A, B, G and H are now finished and fully snagged internally. We are waiting for delivery of the last pieces of expansion joint materials to enable the rest of the communal external area to be completed.

The site was due for handover by the construction company on 1st September but due to a few items still to finish off externally, as well as waiting for the electricity authority to finish the testing and commissioning of the electricity supply to each apartment, we will now take possession of the site on 5th October. Delivery of Plot B (comprising Blocks C, D, E and F) will be on 20th October. This new handover timetable does not affect the delivery of the apartments which are finished and undergoing final snagging ahead of the delivery to clients between 15th September and 15th November.

Kitchen of Block D Townhouse
Kitchen of Block D Townhouse

In the communal external spaces, the Gripstone areas are almost completed and the wooden decking around the pools has begun to be installed.

Installing the wooden decking
Installing the wooden decking

All garden areas have now been planted and the artificial grass installed between Blocks A, H, G and B which gives a cool, calm feeling to the resort.

View from ground floor apartment in B block

View from ground floor apartment in B block

View of resort from upper floor of Block H
View of Block B

View of resort from upper floor of Block H

View of Block B

The utility companies have finished the installation of water and electricity connections around the development so the road construction is now underway. With so much messy work going on around the edges of the resort to complete the roads and pathways we are delaying filling the pools until the end of the month.

Laying out the visitor car park next to Block G

Finishing the main car park of the Spa building

We spent time this week with potential operators of the restaurant and supermarket and also continued with the interviews for resort staff. The Spa building continues to shape up well.

Spa building reception
Spa building reception
Roof top café bar
View from the gym
Roof top café bar

View from the gym


Sound proofed ceiling of the dance studio
Dominic and Joanne in the TV room
Sound proofed ceiling of the dance studio

Dominic and Joanne in the TV room


View of plot B from Spa building

View of plot B from Spa building

Back of Block H

Back of Block H

The underground car parks are finished as are the ramps in and out. The fire shutters will be installed next and the individual car park space markings.

Underground car park entrance
Underground car park exit

Underground car park entrance

Underground car park exit
Underground car park

Underground car park

The next site meeting will take place on Tuesday 5th October.

August 3, 2010

Monthly Progress Meeting 3rd August 2010

The holiday season has well and truly begun - and just as well, as the mercury hit 46 degrees last week in Cyprus with 98% humidity in Larnaca and poor visibility – which is not pleasant when working on a building site. Luckily for the construction workers the site is closed from 7th to 16th August with most businesses across Cyprus taking a full 3 weeks holiday till the end of August.

The team in Liverpool is also taking the opportunity to squeeze in a few days holiday before the handover season begins in September. The office will remain open for the first time this year in the run up to completion but with a reduced staff till the end of the month as we rotate through holidays.

In the final month before completion the last details are being finished across the site.

Across the site
Across the site

The finishing touches are being made to the external areas with the wooden decking being laid around the pool areas and the pathways being finished off.

Wooden decking is laid around the pools
Wooden decking is laid around the pools
Wooden decking is laid around the pools
Central path is laid in front of E block
Finishing the pathways and landscaping
Central path is laid in front of E block Finishing the pathways and landscaping

The Spa building in on track with further work done on the reception area with feature tiling and the floor to ceiling glazing in the gym is being installed, providing a great view of the resort while doing a cardio workout.

The glazing in the gym is installed
The glazing in the gym is installed
The glazing in the gym is installed

The work on the public roads surrounding the development has begun. This is great news as this work is often subject to delay in Cyprus as it is generally not within the control of the developer. However the utility companies have started to lay the cables and pipes necessary to connect the development to the main services. Once this work is finished the public pathways surrounding the development will then be completed.

Trenches are dug for utilities beneath the public pathways around the development
Trenches are dug for utilities beneath the public pathways around the development
Work on the public roads begin
Work on the public roads begin

The interior fit out of the hydrotherapy area continues and the mosaic feature wall of the hydrotherapy pool is finished as is most of the tiling in the pool, Jacuzzi, plunge pool and showers. The wooden walls and seating of the sauna have been installed and construction of the barrelled ceiling of the steam room is underway.

The tiling of the hydrotherapy pool is completed
The tiling of the hydrotherapy pool is completed
The tiling of the hydrotherapy pool is completed

d
The seating is installed in the sauna

The cold plunge pool – brrr!
The steam room takes shape with a barrelled ceiling to avoid drips

The cold plunge pool – brrr!

The steam room takes shape with a barrelled ceiling to avoid drips

The private apartments are virtually finished and are now being systematically cleaned and snagged prior to the formal handover from the construction company on 1st September. Our own staff will then do another snagging inspection of each property before the owners begin to take possession over the coming months.

Balcony of Apartment in G Block with access to private roof terrace
Private roof terrace on G Block

Balcony of Apartment in G Block with access to private roof terrace

Private roof terrace on G Block
Constantinos the architect inspects the external staircase between A and H block with Yiannos the site engineer

Constantinos the architect inspects the external staircase between A and H block with Yiannos the site engineer

G Block
G Block

The construction site is closed until 16th August then it’s all hands on deck to finish plot A by 1st September and plot B by 30th September. The next progress meeting will be on Tuesday 7th September.