October 12, 2009

Monthly Progress Meeting 6th October 2009


The Grove Spa Resort
The Grove Spa Resort

Blocks B, C, E, F and G are all ahead of schedule with the screed laid ready to start tiling.

View from F001
View from F001

Blocks A and H are springing up quickly, catching up on the initial delay.

Front of Block A
Front of Block A

The reception building is now at first floor level and the skylights from the ground floor level into the hydrotherapy area of the basement have been punched through.

Skylights into Hydrotherapy Pool
Skylights into Hydrotherapy Pool

Work continues on the basement and machine room areas of the outdoor pools and the Jacuzzis.

Jacuzzi
Jacuzzi

We have now received all client choices for ceramic tiles and granite as well as the kitchens, wardrobes and internal doors and the 4 sample apartments are being prepared. Thanks to everyone for returning your choices on time.

3 Floors of D Block
3 Floors of D Block

We are spending a lot of time with the interior designer Claire Chrysostomou on the interiors of the Spa building, particularly in the hydrotherapy area with the sauna, steam room and multiple wet areas. New 3D images of these areas will be ready shortly.

d
Hydrotherapy Pool Structure

B Block Roof Gardens
B Block Roof Gardens

Regards

Stephanie